When you report some type of construction defect to your contractor and ask them to address the problem, you’d expect them to do just that. Unfortunately, sometimes, contractors will fail to fix issues they themselves have caused, for one reason or another. In these cases, taking legal action against them may seem like the right next step; however, before you can file a construction defect claim, you have to follow a formal notice process. This process is governed by Chapter 558.
Continue reading and reach out to a competent Florida construction defect lawyer from Ansbacher Law to learn more about how this process works and how our legal team can help you through it. Here are some of the questions you may have:
What Does Florida Chapter 558 Require?
Chapter 558 is Florida’s presuit notice and opportunity to repair law for construction defect claims. Essentially, it gives potentially responsible parties an opportunity to inspect the property and propose a resolution before litigation, though it does not guarantee repairs.
The law can apply to homeowners, subsequent purchasers, and condominium or homeowners’ associations pursuing covered property damage claims. It excludes personal injury claims. Under Florida’s construction defect law, defects may involve the following:
- Materials: Defective products or components used in the property.
- Workmanship: Work that fails to meet accepted trade standards.
- Design: Plans that fail to satisfy applicable professional standards of care.
- Code violations: Qualifying violations of building codes applicable when construction occurred.
You should also have your contract and the project’s completion status reviewed, as an unfinished project or a written agreement to opt out may affect whether this process applies.
How Do You Send a Chapter 558 Notice?
Your notice must reference Chapter 558, describe each alleged defect, and identify its location. Any resulting damage or loss, if known, must also be explained in reasonable detail so the recipient can understand what you are claiming. Some of the requirements for Chapter 558 notices under Section 558.004 are as follows:
- Timing: Generally, notice must be served at least 60 days before filing an action, or 120 days for an association representing more than 20 parcels.
- Recipient: Serve the appropriate contractor, subcontractor, supplier, or design professional, including the contracting party when the claim concerns contracted work.
- Delivery: Use a statutory service method, such as qualifying certified mail, hand delivery, or a courier providing written delivery evidence.
- Documentation: Photographs, inspection findings, and repair estimates can help explain the defects and associated damage.
What Happens After the Notice Is Served?
The recipient has an opportunity to inspect the property and respond to your claim. You must provide reasonable access during normal working hours, while destructive testing requires mutual agreement and compliance with statutory conditions. Some examples of potential responses may include the following:
- An offer to repair the defects at no cost to you.
- A proposed monetary settlement.
- Repairs combined with payment.
- A rejection disputing your claim.
You are not obligated to accept an offer. However, if a timely settlement proposal is received, you must serve written acceptance or rejection within 45 days, and litigation may proceed as permitted by the statute if the claim is rejected or no timely response arrives.
If you have any further questions, or if you’d like to speak with a seasoned Florida construction defect lawyer about your case, please don’t hesitate to reach out to Ansbacher Law for an initial consultation today.