When something is wrong with the way your property was built, getting the damage repaired may seem like the most immediate concern. However, while you are arranging inspections, speaking with the contractor, and trying to determine what those repairs will cost, there is another issue that deserves your attention: the deadline for taking legal action. In the state of Florida, construction defect claims are generally subject to both a statute of limitations and a statute of repose. Continue reading and reach out to a seasoned Florida construction defect lawyer from Ansbacher Law to learn more about the difference between the two and how our firm can effectively represent your interests through each phase of your case. Here are some of the questions you may have:
What Is the Statute of Limitations for Florida Construction Defect Cases?
Florida generally allows four years to file a lawsuit involving the design, planning, or construction of an improvement to real property. However, when that period begins depends on the circumstances. Under Florida Statutes § 95.11(3)(b), the distinction is as follows:
- Apparent defects: The period generally starts with the earliest qualifying certificate or construction abandonment date.
- Latent defects: For hidden defects, the clock begins when the problem is discovered or should have been discovered through reasonable diligence.
How Does the Statute of Repose Differ From the Statute of Limitations?
The statute of repose generally imposes a seven-year outer deadline, regardless of whether the defect has been discovered.
This period ordinarily begins with whichever of the following occurs first:
- A temporary certificate of occupancy is issued.
- A certificate of occupancy is issued.
- A certificate of completion is issued.
- Unfinished construction is abandoned.
The deadlines operate together. For example, if a latent defect is discovered six years after the triggering event, you generally have only one year before repose expires, rather than four more years. You should also note that model homes and projects with multiple buildings have special rules.
What Should Property Owners Do Before Either Deadline Expires?
First, you should speak with an attorney promptly and begin collecting records concerning the construction and damage. You may want a complete repair estimate first, but waiting for every answer can leave little time to investigate. Some of the most important steps that you can take are as follows:
- Document the damage: Take photographs and keep dated notes about leaks, cracks, and recurring problems.
- Gather construction records: Locate contracts, permits, certificates, inspection reports, and warranty documents.
- Keep correspondence: Save messages exchanged with contractors, developers, and anyone who inspected or repaired the property.
- Address notice requirements: Ask whether Chapter 558 applies and how its procedures affect your filing schedule.
Under Florida Statutes § 558.004, properly serving a construction defect notice can pause the applicable statute of limitations. It does not pause the statute of repose, however, so the notice process must be coordinated with the lawsuit deadline.
If you have any additional questions or believe you have a valid claim for a construction defect, please don’t hesitate to contact Ansbacher Law today. We are here to effectively represent your interests, every step of the way.